On July 12, 1962, the Federal Power Commission, now
known as the Federal Energy Regulatory Commission (FERC), issued
Douglas PUD a 50-year license to operate the Wells Project. The FERC
license for the project expires on May 31, 2012. An application for
the new license must be filed on or before May 31, 2010. This FERC license application process is referred to as relicensing. Douglas PUD
is currently pursuing a new operating license
through FERC’s
Integrated Licensing Process (ILP).
|